GATE 2013 ME · Question 64
2 marksMultiple choiceGeneral AptitudePercentages, Ratios, Proportions and Mixtures
The current erection cost of a structure is Rs. 13,200. If the labour wages per day increase by 1/5 of the current wages and the working hours decrease by 1/24 of the current period, then the new cost of erection in *Rs.* is
- A
16,500
- B
15,180
- C
11,000
- D
10,120
GATE 2013 · Mechanical Engineering · IIT Bombay
Answer
(B)
From the official answer key published by IIT Bombay.
Worked solution
The total erection cost depends directly on the wage rate and the total duration (working period) required:
Given:
- Initial cost
- Wages increase by , so the new wage factor is:
- Working period decreases by , so the new time factor is:
The new erection cost is:
Answer: (B) 15,180
Practise Percentages, Ratios, Proportions and Mixtures
9 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.
More from Percentages, Ratios, Proportions and Mixtures
- GATE 2024 ME · Q4The real variables x, y, z, and the real constants p, q, r satisfy x/pq - r2 = y/qr - p2 = z/rp - q2 Given…
- GATE 2022 ME Set 1 · Q2The average of the monthly salaries of M, N and S is ₹ 4000. The average of the monthly salaries of N, S and…
- GATE 2021 ME Set 1 · Q8The number of hens, ducks and goats in farm P are 65, 91 and 169, respectively. The total number of hens,…
- GATE 2020 ME Set 2 · Q5There are five levels {P, Q, R, S, T} in a linear supply chain before a product reaches customers, as shown…
- GATE 2019 ME Set 1 · Q7A person divided an amount of Rs. 100,000 into two parts and invested in two different schemes. In one he…
- GATE 2019 ME Set 2 · Q6Fiscal deficit was 4% of the GDP in 2015 and that increased to 5% in 2016. If the GDP increased by 10% from…
Question from the official GATE 2013 ME paper, IIT Bombay. Solutions by PARIXO AI. All 65 questions of this paper.