A machine produces 0, 1 or 2 defective pieces in a day with associated probability of 1/6, 2/3 and 1/6, respectively. The mean value and the variance of the number of defective pieces produced by the machine in a day, respectively, are

  1. A

    1 and 1/3

  2. B

    1/3 and 1

  3. C

    1 and 4/3

  4. D

    1/3 and 4/3

GATE 2014 · Mechanical Engineering · Set 3 · IIT Kharagpur · printed as Q.28 in the ME section

Answer
(A)

From the official answer key published by IIT Kharagpur.

Worked solution

Let denote the number of defective pieces produced in a day. The probability distribution of is given by:

The mean (expected value) is:

The second moment is:

The variance is:

Thus, the mean is and the variance is .

Answer: (A) 1 and 1/3

Practise Probability & Statistics

41 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.

More from Probability & Statistics

Question from the official GATE 2014 ME paper (Set 3), IIT Kharagpur. Solutions by PARIXO AI. All 65 questions of this paper.