X bullocks and Y tractors take 8 days to plough a field. If we halve the number of bullocks and double the number of tractors, it takes 5 days to plough the same field. How many days will it take X bullocks alone to plough the field?

  1. A

    30

  2. B

    35

  3. C

    40

  4. D

    45

GATE 2017 · Mechanical Engineering · Set 2 · IIT Roorkee

Answer
(A)

From the official answer key published by IIT Roorkee.

Worked solution

Let the rate of work done by bullocks be fields per day, and the rate of work done by tractors be fields per day.

From the first condition, bullocks and tractors complete the field in days:

From the second condition, halving the bullocks gives a rate of , and doubling the tractors gives a rate of . Together they take days:

To eliminate , multiply the first equation by :

Subtract the second equation from this result:


Since bullocks complete of the field per day, they will take:

Answer: (A) 30

Practise Time, Work, Pipes and Motion

16 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.

More from Time, Work, Pipes and Motion

Question from the official GATE 2017 ME paper (Set 2), IIT Roorkee. Solutions by PARIXO AI. All 65 questions of this paper.