GATE 2018 ME Set 2 · Question 8

2 marksMultiple choiceGeneral AptitudeTime, Work, Pipes and Motion

A contract is to be completed in 52 days and 125 identical robots were employed, each operational for 7 hours a day. After 39 days, five-seventh of the work was completed. How many additional robots would be required to complete the work on time, if each robot is now operational for 8 hours a day?

  1. A

    50

  2. B

    89

  3. C

    146

  4. D

    175

GATE 2018 · Mechanical Engineering · Set 2 · IIT Guwahati · printed as Q.8 in the GA section

Answer
Marks to all (the question was dropped)

From the official answer key published by IIT Guwahati.

Worked solution

Let be the total work and be the work rate of one robot per hour.
In the first 39 days, 125 robots working 7 hours/day completed :

The remaining work is:

The time remaining is days. Let be the total number of robots working 8 hours/day to complete the remaining work:

The additional robots required would be , which is not an integer and none of the given options (50, 89, 146, 175) match this calculation. Because of the inconsistency in the problem data, the question was dropped and marks were awarded to all candidates.

Answer: Marks to all (the question was dropped)

Practise Time, Work, Pipes and Motion

16 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.

More from Time, Work, Pipes and Motion

Question from the official GATE 2018 ME paper (Set 2), IIT Guwahati. Solutions by PARIXO AI. All 65 questions of this paper.