The table presents the demand of a product. By simple three-months moving average method, the demand-forecast of the product for the month of September is

| Month | Demand |
| :--- | :--- |
| January | 450 |
| February | 440 |
| March | 460 |
| April | 510 |
| May | 520 |
| June | 495 |
| July | 475 |
| August | 560 |

  1. A

  2. B

  3. C

  4. D

GATE 2019 · Mechanical Engineering · Set 1 · IIT Madras · printed as Q.17 in the ME section

Answer
(B)

From the official answer key published by IIT Madras.

Worked solution

In a simple -period moving average method, the forecast for period is the arithmetic mean of the actual demands of the preceding periods:

For the month of September (), the forecast is based on the actual demands of the immediately preceding three months (June, July, and August):

  • Demand in June,
  • Demand in July,
  • Demand in August,

Substituting the values:

Answer: (B)

Practise Forecasting Models

15 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.

More from Forecasting Models

Question from the official GATE 2019 ME paper (Set 1), IIT Madras. Solutions by PARIXO AI. All 65 questions of this paper.