GATE 2021 ME Set 2 · Question 46
Daily production capacity of a bearing manufacturing company is bearings. The daily demand of the bearing is . The holding cost per year of keeping a bearing in the inventory is ₹ . The setup cost for the production of a batch is ₹ . Assuming working days in a year, the economic batch quantity in number of bearings is ________ (in integer).
GATE 2021 · Mechanical Engineering · Set 2 · IIT Bombay · printed as Q.36 in the ME section
Answer
From the official answer key published by IIT Bombay.
Worked solution
The Economic Batch Quantity () is given by:
Given data:
- Daily demand,
- Daily production capacity,
- Number of working days in a year
- Annual demand,
- Setup cost,
- Inventory holding cost per unit per year,
Substitute the values into the formula:
The integer value is 40249 (which falls within the official range of 40200 to 40300).
Answer: 40249
Practise Deterministic Inventory Models
16 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.
More from Deterministic Inventory Models
- GATE 2020 ME Set 1 · Q58Consider two cases as below. Case 1: A company buys 1000 pieces per year of a certain part from vendor 'X'.…
- GATE 2020 ME Set 2 · Q57For a single item inventory system, the demand is continuous, which is 10000 per year. The replenishment is…
- GATE 2019 ME Set 2 · Q65The annual demand of valves per year in a company is 10,000 units. The current order quantity is 400 valves…
- GATE 2018 ME Set 2 · Q28A local tyre distributor expects to sell approximately 9600 steel belted radial tyres next year. Annual…
- GATE 2016 ME Set 1 · Q64The annual demand for an item is 10,000 units. The unit cost is Rs. 100 and inventory carrying charges are…
- GATE 2016 ME Set 2 · Q64A food processing company uses 25,000 kg of corn flour every year. The quantity-discount price of corn flour…
Question from the official GATE 2021 ME paper (Set 2), IIT Bombay. Solutions by PARIXO AI. All 65 questions of this paper.