GATE 2014 ME Set 2 · Question 29

1 markMultiple choiceIndustrial EngineeringForecasting Models

A component can be produced by any of the four processes I, II, III and IV. The fixed cost and the variable cost for each of the processes are listed below. The most economical process for producing a batch of 100 pieces is

| Process | Fixed cost (in Rs.) | Variable cost per piece (in Rs.) |
| :---: | :---: | :---: |
| I | 20 | 3 |
| II | 50 | 1 |
| III | 40 | 2 |
| IV | 10 | 4 |

  1. A

    I

  2. B

    II

  3. C

    III

  4. D

    IV

GATE 2014 · Mechanical Engineering · Set 2 · IIT Kharagpur · printed as Q.19 in the ME section

Answer
(B)

From the official answer key published by IIT Kharagpur.

Worked solution

The total cost () for producing a batch of quantity is the sum of the fixed cost () and the total variable cost:

Given the batch size pieces, we compute the total cost for each process:

  • Process I:
  • Process II:
  • Process III:
  • Process IV:

Process II yields the lowest total production cost of Rs. 150 for a batch of 100 pieces, making it the most economical choice.

Answer: (B) II

Practise Forecasting Models

15 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.

More from Forecasting Models

Question from the official GATE 2014 ME paper (Set 2), IIT Kharagpur. Solutions by PARIXO AI. All 65 questions of this paper.