GATE 2021 ME Set 2 · Question 53
The demand and forecast of an item for five months are given in the table.
| Month | Demand | Forecast |
| :---: | :---: | :---: |
| April | 225 | 200 |
| May | 220 | 240 |
| June | 285 | 300 |
| July | 290 | 270 |
| August | 250 | 230 |
The Mean Absolute Percent Error (MAPE) in the forecast is \_\_\_\_\_\_\_ % *(round off to two decimal places)*
GATE 2021 · Mechanical Engineering · Set 2 · IIT Bombay · printed as Q.43 in the ME section
Answer
From the official answer key published by IIT Bombay.
Worked solution
The Mean Absolute Percent Error (MAPE) is defined as:
Calculating the absolute percentage error for each of the months:
- April:
- May:
- June:
- July:
- August:
Summing these individual errors and averaging over the 5 months:
Answer: 8.07
Practise Forecasting Models
15 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.
More from Forecasting Models
- GATE 2020 ME Set 2 · Q43The forecast for the monthly demand of a product is given in the table below. | Month | Forecast | Actual…
- GATE 2019 ME Set 1 · Q27The table presents the demand of a product. By simple three-months moving average method, the…
- GATE 2018 ME Set 1 · Q26The time series forecasting method that gives equal weightage to each of the m most recent observations is
- GATE 2016 ME Set 3 · Q64The demand for a two-wheeler was 900 units and 1030 units in April 2015 and May 2015, respectively. The…
- GATE 2015 ME Set 1 · Q44For a canteen, the actual demand for disposable cups was 500 units in January and 600 units in February. The…
- GATE 2015 ME Set 2 · Q35Sales data of a product is given in the following table: | Month | January | February | March | April | May…
Question from the official GATE 2021 ME paper (Set 2), IIT Bombay. Solutions by PARIXO AI. All 65 questions of this paper.