Two models, P and Q, of a product earn profits of Rs. 100 and Rs. 80 per piece, respectively. Production times for P and Q are 5 hours and 3 hours, respectively, while the total production time available is 150 hours. For a total batch size of 40, to maximize profit, the number of units of P to be produced is _______

GATE 2017 · Mechanical Engineering · Set 1 · IIT Roorkee

Answer
15

From the official answer key published by IIT Roorkee.

Worked solution

Let and be the number of units of models P and Q to be produced, respectively.

The objective is to maximize profit:

Subject to the constraints:
1. Total batch size:
2. Total production time:
3. Non-negativity:

Substituting into the time constraint:


Substituting into the objective function:

Since profit is strictly increasing with , maximum profit occurs at the upper limit .

Answer: 15

Practise Linear Programming and Simplex Method

14 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.

More from Linear Programming and Simplex Method

Question from the official GATE 2017 ME paper (Set 1), IIT Roorkee. Solutions by PARIXO AI. All 65 questions of this paper.