2 marksMultiple choiceIndustrial EngineeringSequencing and Scheduling

Four jobs are on order in a factory. As on day 20 of the production calendar, the corresponding due date and work remaining to complete these jobs (in days) are given in the table below.

| Job | Due date | Work remaining (in days) |
| :---: | :---: | :---: |
| M | 26 | 5 |
| N | 24 | 10 |
| O | 28 | 10 |
| P | 31 | 5 |

Which job(s) has/have critical ratio less than unity?

  1. A

    Job N and Job O

  2. B

    Job P

  3. C

    Job O and Job P

  4. D

    Job M and Job N

GATE 2026 · Mechanical Engineering · IIT Guwahati

Answer
(A)

From the official answer key published by IIT Guwahati.

Worked solution

The Critical Ratio () for a job is defined as:

Given current calendar day :

  • Job M:

  • Job N:

  • Job O:

  • Job P:

Jobs N and O have a critical ratio less than unity ().

Answer: (A) Job N and Job O

Practise Sequencing and Scheduling

6 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.

More from Sequencing and Scheduling

Question from the official GATE 2026 ME paper, IIT Guwahati. Solutions by PARIXO AI. All 65 questions of this paper.