GATE 2026 ME · Question 47
Four jobs are on order in a factory. As on day 20 of the production calendar, the corresponding due date and work remaining to complete these jobs (in days) are given in the table below.
| Job | Due date | Work remaining (in days) |
| :---: | :---: | :---: |
| M | 26 | 5 |
| N | 24 | 10 |
| O | 28 | 10 |
| P | 31 | 5 |
Which job(s) has/have critical ratio less than unity?
- A
Job N and Job O
- B
Job P
- C
Job O and Job P
- D
Job M and Job N
GATE 2026 · Mechanical Engineering · IIT Guwahati
Answer
From the official answer key published by IIT Guwahati.
Worked solution
The Critical Ratio () for a job is defined as:
Given current calendar day :
- Job M:
- Job N:
- Job O:
- Job P:
Jobs N and O have a critical ratio less than unity ().
Answer: (A) Job N and Job O
Practise Sequencing and Scheduling
6 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.
More from Sequencing and Scheduling
- GATE 2024 ME · Q34A set of jobs U, V, W, X, Y, Z arrive at time t = 0 to a production line consisting of two workstations in…
- GATE 2022 ME Set 2 · Q41Parts P1-P7 are machined first on a milling machine and then polished at a separate machine. Using the…
- GATE 2021 ME Set 1 · Q38A set of jobs A, B, C, D, E, F, G, H arrive at time t = 0 for processing on turning and grinding machines.…
- GATE 2018 ME Set 1 · Q62Processing times (including setup times) and due dates for six jobs waiting to be processed at a work centre…
- GATE 2017 ME Set 1 · Q52Following data refers to the jobs (P, Q, R, S) which have arrived at a machine for scheduling. The shortest…
Question from the official GATE 2026 ME paper, IIT Guwahati. Solutions by PARIXO AI. All 65 questions of this paper.