GATE 2014 ME Set 2 · Question 60

2 marksNumerical answerIndustrial EngineeringPERT and CPM

A project has four activities P, Q, R and S as shown below.

| Activity | Normal duration (days) | Predecessor | Cost slope (Rs./day) |
| :---: | :---: | :---: | :---: |
| P | 3 | - | 500 |
| Q | 7 | P | 100 |
| R | 4 | P | 400 |
| S | 5 | R | 200 |

The normal cost of the project is Rs. 10,000/- and the overhead cost is Rs. 200/- per day. If the project duration has to be crashed down to 9 days, the total cost (in Rupees) of the project is \_\_\_\_\_\_

GATE 2014 · Mechanical Engineering · Set 2 · IIT Kharagpur · printed as Q.50 in the ME section

Answer
12490 to 12510

From the official answer key published by IIT Kharagpur.

Worked solution

The network has two paths:
1. : Duration (Critical path)
2. : Duration

The initial project duration is . To crash to :

  • Step 1 (Reduce from 12 to 10 days): Only path P-R-S is critical. Among activities on this path (P: 500, R: 400, S: 200), activity S has the lowest cost slope. Crash S by 2 days:


Now, both paths have a duration of 10 days.

  • Step 2 (Reduce from 10 to 9 days): Both paths must be reduced simultaneously.
  • Option A: Crash common activity P (cost ).
  • Option B: Crash S by 1 day and Q by 1 day (cost ).

Option B is cheaper, so crash S and Q each by 1 day:

Total crashing cost .
Overhead cost for 9 days .

Answer: 12500

Practise PERT and CPM