GATE 2014 ME Set 3 · Question 60

2 marksMultiple choiceIndustrial EngineeringPERT and CPM

Consider the given project network, where numbers along various activities represent the normal time. The free float on activity 4-6 and the project duration, respectively, are

Figure 1 for GATE 2014 ME Set 3 question 60
  1. A

  2. B

  3. C

  4. D

GATE 2014 · Mechanical Engineering · Set 3 · IIT Kharagpur · printed as Q.50 in the ME section

Answer
(A)

From the official answer key published by IIT Kharagpur.

Worked solution

First, calculate the earliest event times () moving forward:

The project duration is .

The free float of activity with duration is defined as:

For activity 4-6, with , , and duration :

Thus, the free float on activity 4-6 is 2 and the project duration is 13.

Answer: (A)

Practise PERT and CPM

20 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.

More from PERT and CPM

Question from the official GATE 2014 ME paper (Set 3), IIT Kharagpur. Solutions by PARIXO AI. All 65 questions of this paper.