GATE 2014 ME Set 3 · Question 60
Consider the given project network, where numbers along various activities represent the normal time. The free float on activity 4-6 and the project duration, respectively, are
- A
- B
- C
- D
GATE 2014 · Mechanical Engineering · Set 3 · IIT Kharagpur · printed as Q.50 in the ME section
Answer
From the official answer key published by IIT Kharagpur.
Worked solution
First, calculate the earliest event times () moving forward:
The project duration is .
The free float of activity with duration is defined as:
For activity 4-6, with , , and duration :
Thus, the free float on activity 4-6 is 2 and the project duration is 13.
Answer: (A)
Practise PERT and CPM
20 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.
More from PERT and CPM
- GATE 2014 ME Set 4 · Q60The precedence relations and duration (in days) of activities of a project network are given in the table.…
- GATE 2012 ME · Q54Statement for Linked Answer Questions 54 and 55: For a particular project, eight activities are to be…
- GATE 2012 ME · Q55Statement for Linked Answer Questions 54 and 55: For a particular project, eight activities are to be…
- GATE 2026 ME · Q65The activities of a PERT network and their corresponding activity time estimates (in weeks) i.e., optimistic…
- GATE 2025 ME · Q65A project involves eight activities with the precedence relationship and duration as shown in the table…
- GATE 2022 ME Set 1 · Q42Activities A to K are required to complete a project. The time estimates and the immediate predecessors of…
Question from the official GATE 2014 ME paper (Set 3), IIT Kharagpur. Solutions by PARIXO AI. All 65 questions of this paper.