GATE 2012 ME · Question 55
Statement for Linked Answer Questions 54 and 55:
For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below.
| Activity | Predecessors | Duration (days) |
| :---: | :---: | :---: |
| a | - | 3 |
| b | a | 4 |
| c | a | 5 |
| d | a | 4 |
| e | b | 2 |
| f | d | 9 |
| g | c, e | 6 |
| h | f, g | 2 |
If the duration of activity f alone is changed from 9 to 10 days, then the
- A
critical path remains the same and the total duration to complete the project changes to 19 days.
- B
critical path and the total duration to complete the project remain the same.
- C
critical path changes but the total duration to complete the project remains the same.
- D
critical path changes and the total duration to complete the project changes to 17 days.
GATE 2012 · Mechanical Engineering · IIT Delhi
Answer
No official key survives for this paper; this is PARIXO AI's own answer, not official.
Worked solution
When the duration of activity is changed from to days, the path durations become:
1.
2.
3.
The critical path remains and the total project duration increases to days.
Answer: (A)
Practise PERT and CPM
20 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.
More from PERT and CPM
- GATE 2026 ME · Q65The activities of a PERT network and their corresponding activity time estimates (in weeks) i.e., optimistic…
- GATE 2025 ME · Q65A project involves eight activities with the precedence relationship and duration as shown in the table…
- GATE 2022 ME Set 1 · Q42Activities A to K are required to complete a project. The time estimates and the immediate predecessors of…
- GATE 2022 ME Set 2 · Q59A project consists of five activities (A, B, C, D and E). The duration of each activity follows beta…
- GATE 2021 ME Set 1 · Q45Activities A, B, C and D form the critical path for a project with a PERT network. The means and variances…
- GATE 2021 ME Set 2 · Q18A PERT network has 9 activities on its critical path. The standard deviation of each activity on the…
Question from the official GATE 2012 ME paper, IIT Delhi. Solutions by PARIXO AI. All 65 questions of this paper.