PARIXO GATE · ME Open the app

GATE 2012 ME · Question 55

2 marksMultiple choiceIndustrial EngineeringPERT and CPM

Statement for Linked Answer Questions 54 and 55:

For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below.

| Activity | Predecessors | Duration (days) |
| :---: | :---: | :---: |
| a | - | 3 |
| b | a | 4 |
| c | a | 5 |
| d | a | 4 |
| e | b | 2 |
| f | d | 9 |
| g | c, e | 6 |
| h | f, g | 2 |

If the duration of activity f alone is changed from 9 to 10 days, then the

  1. A

    critical path remains the same and the total duration to complete the project changes to 19 days.

  2. B

    critical path and the total duration to complete the project remain the same.

  3. C

    critical path changes but the total duration to complete the project remains the same.

  4. D

    critical path changes and the total duration to complete the project changes to 17 days.

GATE 2012 · Mechanical Engineering · IIT Delhi

Answer
(A)

No official key survives for this paper; this is PARIXO AI's own answer, not official.

Worked solution

When the duration of activity is changed from to days, the path durations become:
1.
2.
3.

The critical path remains and the total project duration increases to days.

Answer: (A)

Practise PERT and CPM

20 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.

More from PERT and CPM

Question from the official GATE 2012 ME paper, IIT Delhi. Solutions by PARIXO AI. All 65 questions of this paper.