GATE 2014 ME Set 3 · Question 61

2 marksMultiple choiceIndustrial EngineeringDeterministic Inventory Models

A manufacturer can produce bearings per day. The manufacturer received an order of bearings per day from a customer. The cost of holding a bearing in stock is Rs. per month. Setup cost per production run is Rs. . Assuming working days in a year, the frequency of production run should be

  1. A

  2. B

  3. C

  4. D

GATE 2014 · Mechanical Engineering · Set 3 · IIT Kharagpur · printed as Q.51 in the ME section

Answer
(C)

From the official answer key published by IIT Kharagpur.

Worked solution

The Economic Production Quantity ( or ) is given by:

where:

  • Production rate
  • Demand rate
  • Setup cost
  • Working days per year
  • Annual demand
  • Holding cost per unit per year

Substitute these values:

The frequency of production runs (cycle time between successive setups) is:

Answer: (C)

Practise Deterministic Inventory Models

16 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.

More from Deterministic Inventory Models

Question from the official GATE 2014 ME paper (Set 3), IIT Kharagpur. Solutions by PARIXO AI. All 65 questions of this paper.