GATE 2014 ME Set 4 · Question 29
Demand during lead time with associated probabilities is shown below:
| Demand | 50 | 70 | 75 | 80 | 85 |
| :--- | :--- | :--- | :--- | :--- | :--- |
| Probability | 0.15 | 0.14 | 0.21 | 0.20 | 0.30 |
Expected demand during lead time is ______
GATE 2014 · Mechanical Engineering · Set 4 · IIT Kharagpur · printed as Q.19 in the ME section
Answer
From the official answer key published by IIT Kharagpur.
Worked solution
The expected demand during lead time, , is the expected value of the discrete random variable representing demand:
Substituting the given values:
Answer: 74.55 (acceptable range: 74 to 75)