GATE 2014 ME Set 4 · Question 29

1 markNumerical answerIndustrial EngineeringStochastic Inventory & Safety Stock Systems

Demand during lead time with associated probabilities is shown below:

| Demand | 50 | 70 | 75 | 80 | 85 |
| :--- | :--- | :--- | :--- | :--- | :--- |
| Probability | 0.15 | 0.14 | 0.21 | 0.20 | 0.30 |

Expected demand during lead time is ______

GATE 2014 · Mechanical Engineering · Set 4 · IIT Kharagpur · printed as Q.19 in the ME section

Answer
74 to 75

From the official answer key published by IIT Kharagpur.

Worked solution

The expected demand during lead time, , is the expected value of the discrete random variable representing demand:

Substituting the given values:

Answer: 74.55 (acceptable range: 74 to 75)

Practise Stochastic Inventory & Safety Stock Systems

3 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.