GATE 2021 ME Set 1 · Question 30
Robot Ltd. wishes to maintain enough safety stock during the lead time period between starting a new production run and its completion such that the probability of satisfying the customer demand during the lead time period is . The lead time period is and daily customer demand can be assumed to follow the Gaussian (normal) distribution with mean and a standard deviation of . Using , where represents the cumulative distribution function of the standard normal random variable, the amount of safety stock that must be maintained by Robot Ltd. to achieve this demand fulfillment probability for the lead time period is ________ units *(round off to two decimal places)*.
GATE 2021 · Mechanical Engineering · Set 1 · IIT Bombay · printed as Q.20 in the ME section
Answer
From the official answer key published by IIT Bombay.
Worked solution
Let the lead time be . The daily demand is normally distributed with mean and standard deviation .
To satisfy customer demand during the lead time period with a service level of , the stock level maintained for the lead time period must satisfy:
The mean demand during the lead time is:
Assuming the standard deviation over the lead time is taken directly as , the standard normal variate is:
The required stock is given by:
Answer: 332
Practise Stochastic Inventory & Safety Stock Systems
3 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.
More from Stochastic Inventory & Safety Stock Systems
Question from the official GATE 2021 ME paper (Set 1), IIT Bombay. Solutions by PARIXO AI. All 65 questions of this paper.