GATE 2016 ME Set 3 · Question 35

1 markMultiple choiceIndustrial EngineeringPERT and CPM

In PERT chart, the activity time distribution is

  1. A

    Normal

  2. B

    Binomial

  3. C

    Poisson

  4. D

    Beta

GATE 2016 · Mechanical Engineering · Set 3 · IISc Bangalore · printed as Q.25 in the ME section

Answer
(D)

From the official answer key published by IISc Bangalore.

Worked solution

Program Evaluation and Review Technique (PERT) is a probabilistic project management tool used for non-repetitive projects where activity durations are uncertain.

  • The duration of an individual activity in PERT is modeled using a Beta distribution because it is a bounded, unimodal, and generally skewed distribution defined by three time estimates: optimistic time (), most likely time (), and pessimistic time ().
  • By the Central Limit Theorem, the overall project completion time (the sum of durations of independent critical activities) follows a Normal distribution.

Since the question specifically asks for the activity time distribution, it is the Beta distribution.

Answer: (D) Beta

Practise PERT and CPM

20 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.

More from PERT and CPM

Question from the official GATE 2016 ME paper (Set 3), IISc Bangalore. Solutions by PARIXO AI. All 65 questions of this paper.