GATE 2016 ME Set 3 · Question 35
1 markMultiple choiceIndustrial EngineeringPERT and CPM
In PERT chart, the activity time distribution is
- A
Normal
- B
Binomial
- C
Poisson
- D
Beta
GATE 2016 · Mechanical Engineering · Set 3 · IISc Bangalore · printed as Q.25 in the ME section
Answer
(D)
From the official answer key published by IISc Bangalore.
Worked solution
Program Evaluation and Review Technique (PERT) is a probabilistic project management tool used for non-repetitive projects where activity durations are uncertain.
- The duration of an individual activity in PERT is modeled using a Beta distribution because it is a bounded, unimodal, and generally skewed distribution defined by three time estimates: optimistic time (), most likely time (), and pessimistic time ().
- By the Central Limit Theorem, the overall project completion time (the sum of durations of independent critical activities) follows a Normal distribution.
Since the question specifically asks for the activity time distribution, it is the Beta distribution.
Answer: (D) Beta
Practise PERT and CPM
20 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.
More from PERT and CPM
- GATE 2015 ME Set 1 · Q43Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to…
- GATE 2015 ME Set 2 · Q64A project consists of 7 activities. The network along with the time durations (in days) for various…
- GATE 2014 ME Set 2 · Q60A project has four activities P, Q, R and S as shown below. | Activity | Normal duration (days) |…
- GATE 2014 ME Set 3 · Q60Consider the given project network, where numbers along various activities represent the normal time. The…
- GATE 2014 ME Set 4 · Q60The precedence relations and duration (in days) of activities of a project network are given in the table.…
- GATE 2012 ME · Q54Statement for Linked Answer Questions 54 and 55: For a particular project, eight activities are to be…
Question from the official GATE 2016 ME paper (Set 3), IISc Bangalore. Solutions by PARIXO AI. All 65 questions of this paper.