GATE 2019 ME Set 2 · Question 7
Two pipes and can fill a tank in hours and hours respectively, while a third pipe can empty the tank in hours. Initially, and are open for hours. Then is closed and is opened. After more hours is closed. The total time taken to fill the tank (in hours) is ________.
- A
13.50
- B
14.50
- C
15.50
- D
16.50
GATE 2019 · Mechanical Engineering · Set 2 · IIT Madras · printed as Q.7 in the GA section
Answer
From the official answer key published by IIT Madras.
Worked solution
Let the capacity of the tank be the LCM of , , and , which is .
The rates of the pipes are:
- Pipe :
- Pipe :
- Pipe :
The process occurs in three stages:
1. First (P and R open):
2. Next (Q and R open):
Total volume filled after is .
3. Remaining work (only Q open):
Answer: (B) 14.50
Practise Time, Work, Pipes and Motion
16 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.
More from Time, Work, Pipes and Motion
- GATE 2018 ME Set 1 · Q3Seven machines take 7 minutes to make 7 identical toys. At the same rate, how many minutes would it take for…
- GATE 2018 ME Set 1 · Q8From the time the front of a train enters a platform, it takes 25 seconds for the back of the train to leave…
- GATE 2018 ME Set 2 · Q8A contract is to be completed in 52 days and 125 identical robots were employed, each operational for 7…
- GATE 2017 ME Set 2 · Q62X bullocks and Y tractors take 8 days to plough a field. If we halve the number of bullocks and double the…
- GATE 2016 ME Set 1 · Q10P, Q, R and S are working on a project. Q can finish the task in 25 days, working alone for 12 hours a day.…
- GATE 2016 ME Set 3 · Q5S, M, E and F are working in shifts in a team to finish a project. M works with twice the efficiency of…
Question from the official GATE 2019 ME paper (Set 2), IIT Madras. Solutions by PARIXO AI. All 65 questions of this paper.