PARIXO GATE · ME Open the app

GATE 2020 ME Set 2 · Question 8

2 marksMultiple choiceGeneral AptitudeTime, Work, Pipes and Motion

It was estimated that 52 men can complete a strip in a newly constructed highway connecting cities P and Q in 10 days. Due to an emergency, 12 men were sent to another project. How many number of days, more than the original estimate, will be required to complete the strip?

  1. A

    3 days

  2. B

    5 days

  3. C

    10 days

  4. D

    13 days

GATE 2020 · Mechanical Engineering · Set 2 · IIT Delhi · printed as Q.8 in the GA section

Answer
(A)

From the official answer key published by IIT Delhi.

Worked solution

The total work required to complete the strip is constant and given in terms of man-days:

When 12 men are reassigned to another project, the remaining number of men is:

Let be the number of days required for the remaining men to complete the same work:

The question asks for the number of days *more than the original estimate*:

Answer: (A) 3 days

Practise Time, Work, Pipes and Motion

16 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.

More from Time, Work, Pipes and Motion

Question from the official GATE 2020 ME paper (Set 2), IIT Delhi. Solutions by PARIXO AI. All 65 questions of this paper.