GATE 2020 ME Set 2 · Question 8
It was estimated that 52 men can complete a strip in a newly constructed highway connecting cities P and Q in 10 days. Due to an emergency, 12 men were sent to another project. How many number of days, more than the original estimate, will be required to complete the strip?
- A
3 days
- B
5 days
- C
10 days
- D
13 days
GATE 2020 · Mechanical Engineering · Set 2 · IIT Delhi · printed as Q.8 in the GA section
Answer
From the official answer key published by IIT Delhi.
Worked solution
The total work required to complete the strip is constant and given in terms of man-days:
When 12 men are reassigned to another project, the remaining number of men is:
Let be the number of days required for the remaining men to complete the same work:
The question asks for the number of days *more than the original estimate*:
Answer: (A) 3 days
Practise Time, Work, Pipes and Motion
16 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.
More from Time, Work, Pipes and Motion
- GATE 2019 ME Set 2 · Q7Two pipes P and Q can fill a tank in 6 hours and 9 hours respectively, while a third pipe R can empty the…
- GATE 2018 ME Set 1 · Q3Seven machines take 7 minutes to make 7 identical toys. At the same rate, how many minutes would it take for…
- GATE 2018 ME Set 1 · Q8From the time the front of a train enters a platform, it takes 25 seconds for the back of the train to leave…
- GATE 2018 ME Set 2 · Q8A contract is to be completed in 52 days and 125 identical robots were employed, each operational for 7…
- GATE 2017 ME Set 2 · Q62X bullocks and Y tractors take 8 days to plough a field. If we halve the number of bullocks and double the…
- GATE 2016 ME Set 1 · Q10P, Q, R and S are working on a project. Q can finish the task in 25 days, working alone for 12 hours a day.…
Question from the official GATE 2020 ME paper (Set 2), IIT Delhi. Solutions by PARIXO AI. All 65 questions of this paper.