GATE 2021 ME Set 1 · Question 45
Activities A, B, C and D form the critical path for a project with a PERT network. The means and variances of the activity duration for each activity are given below. All activity durations follow the Gaussian (normal) distribution, and are independent of each other.
| Activity | A | B | C | D |
| :--- | :---: | :---: | :---: | :---: |
| Mean (days) | 6 | 11 | 8 | 15 |
| Variance (days) | 4 | 9 | 4 | 9 |
The probability that the project will be completed within 40 days is ______ (round off to two decimal places).
(Note: Probability is a number between 0 and 1).
GATE 2021 · Mechanical Engineering · Set 1 · IIT Bombay · printed as Q.35 in the ME section
Answer
From the official answer key published by IIT Bombay.
Worked solution
For a PERT network, the total project duration along the critical path is the sum of the durations of the critical activities. Since all activity durations are independent and normally distributed, the project completion time also follows a normal distribution:
To find the probability that the project will be completed within days, we compute the standard normal variable :
The probability is:
Answer: 0.5
Practise PERT and CPM
20 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.
More from PERT and CPM
- GATE 2021 ME Set 2 · Q18A PERT network has 9 activities on its critical path. The standard deviation of each activity on the…
- GATE 2020 ME Set 1 · Q23In the Critical Path Method (CPM), the cost-time slope of an activity is given by
- GATE 2020 ME Set 2 · Q33Consider the following network of activities, with each activity named A–L, illustrated in the nodes of the…
- GATE 2019 ME Set 1 · Q65A project consists of six activities. The immediate predecessor of each activity and the estimated duration…
- GATE 2019 ME Set 2 · Q45The activities of a project, their duration and the precedence relationships are given in the table. For…
- GATE 2017 ME Set 2 · Q49A project starts with activity A and ends with activity F. The precedence relation and durations of the…
Question from the official GATE 2021 ME paper (Set 1), IIT Bombay. Solutions by PARIXO AI. All 65 questions of this paper.