GATE 2021 ME Set 1 · Question 45

2 marksNumerical answerIndustrial EngineeringPERT and CPM

Activities A, B, C and D form the critical path for a project with a PERT network. The means and variances of the activity duration for each activity are given below. All activity durations follow the Gaussian (normal) distribution, and are independent of each other.

| Activity | A | B | C | D |
| :--- | :---: | :---: | :---: | :---: |
| Mean (days) | 6 | 11 | 8 | 15 |
| Variance (days) | 4 | 9 | 4 | 9 |

The probability that the project will be completed within 40 days is ______ (round off to two decimal places).

(Note: Probability is a number between 0 and 1).

GATE 2021 · Mechanical Engineering · Set 1 · IIT Bombay · printed as Q.35 in the ME section

Answer
0.5

From the official answer key published by IIT Bombay.

Worked solution

For a PERT network, the total project duration along the critical path is the sum of the durations of the critical activities. Since all activity durations are independent and normally distributed, the project completion time also follows a normal distribution:

To find the probability that the project will be completed within days, we compute the standard normal variable :

The probability is:

Answer: 0.5

Practise PERT and CPM

20 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.

More from PERT and CPM

Question from the official GATE 2021 ME paper (Set 1), IIT Bombay. Solutions by PARIXO AI. All 65 questions of this paper.