GATE 2020 ME Set 1 · Question 23
In the Critical Path Method (CPM), the cost-time slope of an activity is given by
- A
- B
- C
- D
GATE 2020 · Mechanical Engineering · Set 1 · IIT Delhi · printed as Q.13 in the ME section
Answer
From the official answer key published by IIT Delhi.
Worked solution
In the Critical Path Method (CPM), project crashing involves expediting an activity's duration from its normal time () to its crash time () at an increased cost, changing from normal cost () to crash cost ().
Assuming a linear direct-cost relationship with time, the cost-time slope represents the incremental cost required to reduce activity duration by one unit of time:
Since and , both the numerator and denominator are positive values.
Answer: (D)
Practise PERT and CPM
20 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.
More from PERT and CPM
- GATE 2020 ME Set 2 · Q33Consider the following network of activities, with each activity named A–L, illustrated in the nodes of the…
- GATE 2019 ME Set 1 · Q65A project consists of six activities. The immediate predecessor of each activity and the estimated duration…
- GATE 2019 ME Set 2 · Q45The activities of a project, their duration and the precedence relationships are given in the table. For…
- GATE 2017 ME Set 2 · Q49A project starts with activity A and ends with activity F. The precedence relation and durations of the…
- GATE 2016 ME Set 2 · Q65A project consists of 14 activities, A to N. The duration of these activities (in days) are shown in…
- GATE 2016 ME Set 3 · Q35In PERT chart, the activity time distribution is
Question from the official GATE 2020 ME paper (Set 1), IIT Delhi. Solutions by PARIXO AI. All 65 questions of this paper.