GATE 2020 ME Set 1 · Question 23

1 markMultiple choiceIndustrial EngineeringPERT and CPM

In the Critical Path Method (CPM), the cost-time slope of an activity is given by

  1. A

  2. B

  3. C

  4. D

GATE 2020 · Mechanical Engineering · Set 1 · IIT Delhi · printed as Q.13 in the ME section

Answer
(D)

From the official answer key published by IIT Delhi.

Worked solution

In the Critical Path Method (CPM), project crashing involves expediting an activity's duration from its normal time () to its crash time () at an increased cost, changing from normal cost () to crash cost ().

Assuming a linear direct-cost relationship with time, the cost-time slope represents the incremental cost required to reduce activity duration by one unit of time:

Since and , both the numerator and denominator are positive values.

Answer: (D)

Practise PERT and CPM

20 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.

More from PERT and CPM

Question from the official GATE 2020 ME paper (Set 1), IIT Delhi. Solutions by PARIXO AI. All 65 questions of this paper.