GATE 2021 ME Set 2 · Question 18
A PERT network has 9 activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is
- A
3
- B
9
- C
27
- D
81
GATE 2021 · Mechanical Engineering · Set 2 · IIT Bombay · printed as Q.8 in the ME section
Answer
From the official answer key published by IIT Bombay.
Worked solution
In a PERT network, the duration of activities along the critical path are assumed to be independent random variables. Therefore, the total variance of the critical path () is the sum of the variances of individual activities on the critical path:
Given:
- Number of activities on the critical path,
- Standard deviation of each activity,
The variance of each activity is:
The total variance of the critical path is:
Thus, the standard deviation of the critical path is:
Answer: (B) 9
Practise PERT and CPM
20 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.
More from PERT and CPM
- GATE 2020 ME Set 1 · Q23In the Critical Path Method (CPM), the cost-time slope of an activity is given by
- GATE 2020 ME Set 2 · Q33Consider the following network of activities, with each activity named A–L, illustrated in the nodes of the…
- GATE 2019 ME Set 1 · Q65A project consists of six activities. The immediate predecessor of each activity and the estimated duration…
- GATE 2019 ME Set 2 · Q45The activities of a project, their duration and the precedence relationships are given in the table. For…
- GATE 2017 ME Set 2 · Q49A project starts with activity A and ends with activity F. The precedence relation and durations of the…
- GATE 2016 ME Set 2 · Q65A project consists of 14 activities, A to N. The duration of these activities (in days) are shown in…
Question from the official GATE 2021 ME paper (Set 2), IIT Bombay. Solutions by PARIXO AI. All 65 questions of this paper.