GATE 2021 ME Set 2 · Question 18

1 markMultiple choiceIndustrial EngineeringPERT and CPM

A PERT network has 9 activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is

  1. A

    3

  2. B

    9

  3. C

    27

  4. D

    81

GATE 2021 · Mechanical Engineering · Set 2 · IIT Bombay · printed as Q.8 in the ME section

Answer
(B)

From the official answer key published by IIT Bombay.

Worked solution

In a PERT network, the duration of activities along the critical path are assumed to be independent random variables. Therefore, the total variance of the critical path () is the sum of the variances of individual activities on the critical path:

Given:

  • Number of activities on the critical path,
  • Standard deviation of each activity,

The variance of each activity is:

The total variance of the critical path is:

Thus, the standard deviation of the critical path is:

Answer: (B) 9

Practise PERT and CPM

20 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.

More from PERT and CPM

Question from the official GATE 2021 ME paper (Set 2), IIT Bombay. Solutions by PARIXO AI. All 65 questions of this paper.