GATE 2016 ME Set 2 · Question 65
A project consists of 14 activities, A to N. The duration of these activities (in days) are shown in brackets on the network diagram. The latest finish time (in days) for node 10 is _________
GATE 2016 · Mechanical Engineering · Set 2 · IISc Bangalore · printed as Q.55 in the ME section
Answer
From the official answer key published by IISc Bangalore.
Worked solution
To find the latest finish time (latest allowable occurrence time, ) for node 10, we first determine the critical path and project completion time using the forward pass, followed by the backward pass.
Forward Pass (Earliest Times, ):
Backward Pass (Latest Times, ):
Answer: 14
Practise PERT and CPM
20 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.
More from PERT and CPM
- GATE 2016 ME Set 3 · Q35In PERT chart, the activity time distribution is
- GATE 2015 ME Set 1 · Q43Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to…
- GATE 2015 ME Set 2 · Q64A project consists of 7 activities. The network along with the time durations (in days) for various…
- GATE 2014 ME Set 2 · Q60A project has four activities P, Q, R and S as shown below. | Activity | Normal duration (days) |…
- GATE 2014 ME Set 3 · Q60Consider the given project network, where numbers along various activities represent the normal time. The…
- GATE 2014 ME Set 4 · Q60The precedence relations and duration (in days) of activities of a project network are given in the table.…
Question from the official GATE 2016 ME paper (Set 2), IISc Bangalore. Solutions by PARIXO AI. All 65 questions of this paper.