Two mild steel plates of similar thickness, in butt-joint configuration, are welded by gas tungsten arc welding process using the following welding parameters.
| Welding voltage | 20 V |
| :--- | :--- |
| Welding current | 150 A |
| Welding speed | 5 mm/s |
A filler wire of the same mild steel material having diameter is used in this welding process. The filler wire feed rate is selected such that the final weld bead is composed of volume of filler and volume of plate material. The heat required to melt the mild steel material is . The heat transfer factor is and melting factor is . The feed rate of the filler wire is _______ *(round off to one decimal place)*.
GATE 2022 · Mechanical Engineering · Set 1 · IIT Kharagpur
Answer
From the official answer key published by IIT Kharagpur.
Worked solution
The total power supplied by the welding arc is:
The rate of heat utilized for melting the material is:
Given the specific energy required to melt the steel is , the total volume melting rate of the weld bead (filler plus base plate) is:
Since the weld bead is composed of filler wire material by volume, the volume rate of filler wire melted is:
For a filler wire of diameter , the cross-sectional area is:
Therefore, the feed rate of the filler wire is:
Answer: 10.7
Practise Welding I: Physics, Power Sources and Arc Welding
18 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.
More from Welding I: Physics, Power Sources and Arc Welding
- GATE 2022 ME Set 2 · Q57In a direct current arc welding process, the power source has an open circuit voltage of 100 V and short…
- GATE 2020 ME Set 2 · Q20Two plates, each of 6 mm thickness, are to be butt-welded. Consider the following processes and select the…
- GATE 2019 ME Set 2 · Q61A gas tungsten arc welding operation is performed using a current of 250 A and an arc voltage of 20 V at a…
- GATE 2018 ME Set 1 · Q22The type of weld represented by the shaded region in the figure is
- GATE 2018 ME Set 2 · Q63A welding operation is being performed with voltage = 30 V and current = 100 A. The cross-sectional area of…
- GATE 2017 ME Set 1 · Q23In an arc welding process, welding speed is doubled. Assuming all other process parameters to be constant,…
Question from the official GATE 2022 ME paper (Set 1), IIT Kharagpur. Solutions by PARIXO AI. All 65 questions of this paper.