GATE 2022 ME Set 2 · Question 59
A project consists of five activities (A, B, C, D and E). The duration of each activity follows beta distribution. The three time estimates (in weeks) of each activity and immediate predecessor(s) are listed in the table. The expected time of the project completion is ________ weeks *(in integer)*.
| Activity | Optimistic time | Most likely time | Pessimistic time | Immediate predecessor(s) |
| :---: | :---: | :---: | :---: | :---: |
| A | 4 | 5 | 6 | None |
| B | 1 | 3 | 5 | A |
| C | 1 | 2 | 3 | A |
| D | 2 | 4 | 6 | C |
| E | 3 | 4 | 5 | B, D |
GATE 2022 · Mechanical Engineering · Set 2 · IIT Kharagpur
Answer
From the official answer key published by IIT Kharagpur.
Worked solution
The expected duration of each activity in a PERT network is calculated using:
Calculating for each activity:
- Activity A:
- Activity B:
- Activity C:
- Activity D:
- Activity E:
Determining the path durations from the precedence relationships:
1. Path A B E:
2. Path A C D E:
The expected time of project completion is the duration of the critical path:
Answer: 15
Practise PERT and CPM
20 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.
More from PERT and CPM
- GATE 2021 ME Set 1 · Q45Activities A, B, C and D form the critical path for a project with a PERT network. The means and variances…
- GATE 2021 ME Set 2 · Q18A PERT network has 9 activities on its critical path. The standard deviation of each activity on the…
- GATE 2020 ME Set 1 · Q23In the Critical Path Method (CPM), the cost-time slope of an activity is given by
- GATE 2020 ME Set 2 · Q33Consider the following network of activities, with each activity named A–L, illustrated in the nodes of the…
- GATE 2019 ME Set 1 · Q65A project consists of six activities. The immediate predecessor of each activity and the estimated duration…
- GATE 2019 ME Set 2 · Q45The activities of a project, their duration and the precedence relationships are given in the table. For…
Question from the official GATE 2022 ME paper (Set 2), IIT Kharagpur. Solutions by PARIXO AI. All 65 questions of this paper.