GATE 2021 ME Set 2 · Question 39
A factory produces () products, each of which requires processing on () workstations. Let be the amount of processing time that one unit of the product requires on the workstation. Let the revenue from selling one unit of the product be and be the holding cost per unit per time period for the product. The planning horizon consists of () time periods. The minimum demand that must be satisfied in time period is , and the capacity of the workstation in time period is . Consider the aggregate planning formulation below, with decision variables (amount of product sold in time period ), (amount of product manufactured in time period ) and (amount of product held in inventory at the end of time period .
The capacity constraints and inventory balance constraints for this formulation are
- A
- B
- C
- D
GATE 2021 · Mechanical Engineering · Set 2 · IIT Bombay · printed as Q.29 in the ME section
Answer
From the official answer key published by IIT Bombay.
Worked solution
The aggregate planning model requires two fundamental types of constraints:
1. Capacity constraints: The total time required on workstation during period by all products manufactured cannot exceed the available capacity of that workstation:
Here, the summation is over all products , and the limit applies for each workstation and time period .
2. Inventory balance constraints: For each product in period , the ending inventory equals the beginning inventory (ending inventory of the previous period, ) plus production during period () minus sales during period ():
Option (B) incorrectly subtracts demand instead of actual sales . Options (C) and (D) mistakenly use instead of capacity in the capacity constraint.
Answer: (A)
Practise Aggregate Planning, MRP and Lean Manufacturing
5 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.
More from Aggregate Planning, MRP and Lean Manufacturing
- GATE 2020 ME Set 1 · Q43For an assembly line, the production rate was 4 pieces per hour and the average processing time was 60…
- GATE 2020 ME Set 2 · Q23In Materials Requirement Planning, if the inventory holding cost is very high and the setup cost is zero,…
- GATE 2012 ME · Q13Which one of the following is NOT a decision taken during the aggregate production planning stage?
- GATE 2022 ME Set 1 · Q59The product structure diagram shows the number of different components required at each level to produce one…
Question from the official GATE 2021 ME paper (Set 2), IIT Bombay. Solutions by PARIXO AI. All 65 questions of this paper.