GATE 2012 ME · Question 13

1 markMultiple choiceIndustrial EngineeringAggregate Planning, MRP and Lean Manufacturing

Which one of the following is NOT a decision taken during the aggregate production planning stage?

  1. A

    Scheduling of machines

  2. B

    Amount of labour to be committed

  3. C

    Rate at which production should happen

  4. D

    Inventory to be carried forward

GATE 2012 · Mechanical Engineering · IIT Delhi

Answer
(A)

No official key survives for this paper; this is PARIXO AI's own answer, not official.

Worked solution

Aggregate Production Planning (APP) is an intermediate-range capacity planning activity, typically spanning 3 to 18 months. It focuses on high-level decisions such as overall production rates, workforce levels (amount of labor to be hired or retained), inventory to be carried over between periods, and subcontracting.

In contrast, detailed decisions like the sequencing of jobs and the scheduling of individual machines are short-term operational decisions handled at the shop-floor control or operations scheduling level.

Answer: (A)

Practise Aggregate Planning, MRP and Lean Manufacturing

5 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.

More from Aggregate Planning, MRP and Lean Manufacturing

Question from the official GATE 2012 ME paper, IIT Delhi. Solutions by PARIXO AI. All 65 questions of this paper.