GATE 2012 ME · Question 13
Which one of the following is NOT a decision taken during the aggregate production planning stage?
- A
Scheduling of machines
- B
Amount of labour to be committed
- C
Rate at which production should happen
- D
Inventory to be carried forward
GATE 2012 · Mechanical Engineering · IIT Delhi
Answer
No official key survives for this paper; this is PARIXO AI's own answer, not official.
Worked solution
Aggregate Production Planning (APP) is an intermediate-range capacity planning activity, typically spanning 3 to 18 months. It focuses on high-level decisions such as overall production rates, workforce levels (amount of labor to be hired or retained), inventory to be carried over between periods, and subcontracting.
In contrast, detailed decisions like the sequencing of jobs and the scheduling of individual machines are short-term operational decisions handled at the shop-floor control or operations scheduling level.
Answer: (A)
Practise Aggregate Planning, MRP and Lean Manufacturing
5 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.
More from Aggregate Planning, MRP and Lean Manufacturing
- GATE 2022 ME Set 1 · Q59The product structure diagram shows the number of different components required at each level to produce one…
- GATE 2021 ME Set 2 · Q39A factory produces m (i = 1, 2, , m) products, each of which requires processing on n (j = 1, 2, , n)…
- GATE 2020 ME Set 1 · Q43For an assembly line, the production rate was 4 pieces per hour and the average processing time was 60…
- GATE 2020 ME Set 2 · Q23In Materials Requirement Planning, if the inventory holding cost is very high and the setup cost is zero,…
Question from the official GATE 2012 ME paper, IIT Delhi. Solutions by PARIXO AI. All 65 questions of this paper.