For an assembly line, the production rate was 4 pieces per hour and the average processing time was 60 minutes. The WIP inventory was calculated. Now, the production rate is kept the same, and the average processing time is brought down by 30 percent. As a result of this change in the processing time, the WIP inventory

  1. A

    decreases by 25%

  2. B

    increases by 25%

  3. C

    decreases by 30%

  4. D

    increases by 30%

GATE 2020 · Mechanical Engineering · Set 1 · IIT Delhi · printed as Q.33 in the ME section

Answer
(C)

From the official answer key published by IIT Delhi.

Worked solution

By Little's Law, the Work-in-Process (WIP) inventory is given by:

Initially, let the production rate be and the processing time be . The initial WIP is:

In the revised process:

  • The production rate is unchanged:
  • The processing time is reduced by :

The new WIP inventory is:

Therefore, the percentage change in WIP is:

The WIP inventory decreases by .

Answer: (C) decreases by 30%

Practise Aggregate Planning, MRP and Lean Manufacturing

5 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.

More from Aggregate Planning, MRP and Lean Manufacturing

Question from the official GATE 2020 ME paper (Set 1), IIT Delhi. Solutions by PARIXO AI. All 65 questions of this paper.