GATE 2020 ME Set 2 · Question 23
1 markMultiple choiceIndustrial EngineeringAggregate Planning, MRP and Lean Manufacturing
In Materials Requirement Planning, if the inventory holding cost is very high and the setup cost is zero, which one of the following lot sizing approaches should be used?
- A
Economic Order Quantity
- B
Lot-for-Lot
- C
Base Stock Level
- D
Fixed Period Quantity, for 2 periods
GATE 2020 · Mechanical Engineering · Set 2 · IIT Delhi · printed as Q.13 in the ME section
Answer
(B)
From the official answer key published by IIT Delhi.
Practise Aggregate Planning, MRP and Lean Manufacturing
5 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.
More from Aggregate Planning, MRP and Lean Manufacturing
- GATE 2012 ME · Q13Which one of the following is NOT a decision taken during the aggregate production planning stage?
- GATE 2022 ME Set 1 · Q59The product structure diagram shows the number of different components required at each level to produce one…
- GATE 2021 ME Set 2 · Q39A factory produces m (i = 1, 2, , m) products, each of which requires processing on n (j = 1, 2, , n)…
- GATE 2020 ME Set 1 · Q43For an assembly line, the production rate was 4 pieces per hour and the average processing time was 60…
Question from the official GATE 2020 ME paper (Set 2), IIT Delhi. Solutions by PARIXO AI. All 65 questions of this paper.