GATE 2014 ME Set 4 · Question 63
A cylindrical riser of diameter and height has to be designed for a sand casting mould for producing a steel rectangular plate casting of dimensions having the total solidification time of . The total solidification time (in minute) of the riser is _______
GATE 2014 · Mechanical Engineering · Set 4 · IIT Kharagpur · printed as Q.53 in the ME section
Answer
From the official answer key published by IIT Kharagpur.
Worked solution
According to Chvorinov's rule, total solidification time is:
where is the modulus of the casting.
For the plate casting of dimensions :
Using :
For the cylindrical riser (, ):
- Volume,
- If considered as a side riser (both ends cooling):
- If considered as a top riser (one end insulated by casting contact):
Both interpretations yield values within the accepted range of to .
Answer: 3.0
Practise Casting: Patterns, Moulds, Gating and Solidification
34 GATE questions from this chapter, in short untimed sets, with the formula sheet beside them. Free.
More from Casting: Patterns, Moulds, Gating and Solidification
- GATE 2013 ME · Q16A cube shaped casting solidifies in 5 min. The solidification time in min for a cube of the same material,…
- GATE 2026 ME · Q30In relation to metal casting defects, match the following | Defect | | Description | | | :--- | :--- | :---…
- GATE 2025 ME · Q34A liquid metal is poured in a mold cavity of size 200 mm × 200 mm × 200 mm. The cooling is uniform in all…
- GATE 2025 ME · Q38Match the mold elements in the casting process with the most suitable function | Mold element | | Function |…
- GATE 2025 ME · Q62Two metal parts (a cylinder and a cube) of same volume are cast under identical conditions. The diameter of…
- GATE 2024 ME · Q31The allowance provided to a pattern for easy withdrawal from a sand mold is
Question from the official GATE 2014 ME paper (Set 4), IIT Kharagpur. Solutions by PARIXO AI. All 65 questions of this paper.